Another week in the books and more progress on the fuselage is made.  

finished L&R step attach assembly's

the bottom skin is clecoed to the Baggage ribs and step attach assembly's for  reveting

the finished mid fuse lower section

Start section 27 Firewall   the finished L&R firewall angles

he L&R firewall sides are dimpled

the firewall sides are ready for assembly

the L&R sides are mated to the firewall top , fuel tank sealant is applied to the bottom aft side of the firewall top and the assembly is clecoed together with the L&R tunnel assemblies for riveting

the firewall assembly is riveted


The sections are positioned together "Makes me want to sit in it and make airplane sounds" says builder Allen.

"Section 27" of the fuselage is completed!